P
Written by Phillip Williams-Oliveira

If your company has branches set up as a national account on VendorPM, your head office can upload one document or request one exemption for several branches at once, then send everything for a client to VendorPM for review in one step.

This is available when VendorPM has set your company up with branch accounts, and only to users on the head office account who can manage branch compliance. Contact VendorPM to set it up.

Where to find it

  1. In the left navigation, under Manage, click Compliance.

  2. Click Switch to “Manage all branches”.

  3. On the Compliance tab, click Become compliant (or View) next to the client. The Submit compliance requirements page opens.

Choose a requirement and branches

  1. In the Checklist, click the requirement you want to work on. Each one shows how many branches it applies to.

  2. Read the client's instructions for the requirement.

  3. Under Select branches to submit requirement / request exemption, check the branches. Use Search branches..., Province or Status to narrow the list, and Select all to check every branch shown. Branches whose document is already accepted have no checkbox.

Upload one document for several branches

  1. At the bottom of the page, click Upload requirement. The button shows how many branches you selected.

  2. Add the file, then click Save.

The document is staged: it's saved for those branches but not sent yet. Each branch now shows Uploaded.

Request one exemption for several branches

  1. At the bottom of the page, click Request exemption.

  2. Under Exemption Reason, explain why the requirement doesn't apply to the selected branches. Use at least 30 characters.

  3. Click Request exemption.

The exemption request is staged for those branches, and each one now shows Requesting exemption.

Send everything for review

  1. Repeat for any other requirements and branches.

  2. Click Submit changes for review.

Everything staged for this client, across every requirement and branch, is sent to VendorPM in one step, and you return to the Compliance page. VendorPM reviews and approves documents within 1-3 business days. After that, your client can see them.

Change something before you submit

To change what you staged for one branch, click the pencil icon on that branch's row and upload a different document or write a new exemption reason. Once you've submitted, you can't change it here.

Good to know

  • Staged items stay saved until you submit them, so you can come back later.

  • A branch only appears on a client's page once it has finished onboarding with that client.

  • You can't stage anything for a branch that already has a document or exemption request under review for that requirement. The page tells you which branches were skipped and why.

  • Account numbers are different for each branch, so you can't upload them here. Enter them from each branch's own compliance page.

  • Each branch accepts the client's terms and conditions from its own compliance page.

  • If some items couldn't be submitted, the page lists them with the reason and whether they're still staged.

  • Requirements for specific properties are on the Properties tab instead.

Related articles